Fanuc Power Mate i-D/H Maintenance Manual

B63175EN/03
G. MAINTENANCE USING A NOTEBOOK
PERSONAL COMPUTER
APPENDIX
567
This section explains procedures for using the DPL/MDI operation
package for maintenance.
(1)To use executable program for normal operation DPLMDI.EXE
Follow the procedure below with the power to the Power Mate i turned
on to use the DPL/MDI operation package:
1) Confirm that the power to the personal computer is turned
off(NOTE). Then, connect CH2 (see additional information 1
) on
the punch panel on the Power Mate i and RS232C port 1 on the
personal computer (the personal computer port available for the
DPL/MDI operation package is fixed to COM1) using an
RS232C cable.
2) Use the maintenance button and LED display on the Power Mate
i main unit to set the channel to be connected. (See additional
information 2.)
3) Turn the power to the personal computer on to start up Windows.
4) Start the DPL/MDI operation package (DPLMDI.EXE).
5) Perform maintenance. (See V.)
6) Terminate the DPL/MDI operation package.
7) Terminate Windows and turn the power to the personal computer
off.
8) Disconnect the RS232C cable from the punch panel on the
Power Mate i.
9) Use the maintenance button and LED display on the Power Mate
i main unit to restore the channel settings to the initial status. (See
additional information 2.)
(2)To use executable program for boot system and initial operations
BOOTINIT.EXE
To use the DPL/MDI operation package for boot system operation or
memory clear or another initialization, the procedure depends on
whether the system starts up normally. Follow the appropriate
procedure below to perform operation.
When the system can be started up
Turn the power to the Power Mate i on and start up the system, then
perform the following operations:
1) Confirm that the power to the personal computer is turned
off(NOTE). Then, connect CH2 (see additional information 1
) on
the punch panel on the Power Mate i and RS232C port 1 on the
personal computer (the personal computer port available for the
DPL/MDI operation package is fixed to COM1) using an
RS232C cable.
2) Use the maintenance button and LED display on the Power Mate
i main unit to set the channel to be connected. (See additional
information 2.)
3) Turn the power to the Power Mate i off.
4) Turn the power to the personal computer on to start up Windows.
5) Start the DPL/MDI operation package (for boot operation)
(BOOTINIT.EXE).
6) Turn the power to the Power Mate i on.
7) Perform boot system operation or initialization. (See G.4.)